Construction Phasing

In order to ensure the continuation of the existing services to the south of Nanny Cay, the construction of the new marina and amenities will be divided into two main phases, fundamentally split between sea side and land side construction.

Construction started on January 30, 2026

Phase 1 – Sea side and boatyard

  • Construction of a new 112 slip South Marina
  • Construction of the breakwater (the armour wall) to contain, shelter and protect the new South Marina
  • Reclamation, and expansion of the existing boatyard
  • Construction of a new 150 ton haul out facility to accommodate servicing of yachts up to 120 feet in length and 44 feet in width

Estimated construction time: 16 months

Phase 2 – Land side

Construction of:

  • Concierge facility, including shower and bathroom facilities
  • Marine Hub with Royal BVI Yacht Club and HLSCC Marine Centre
  • Regatta and Event Village
  • Food and Retail outlets
  • Beach
  • Beach bar and facilities
  • Addition of new parking facilities, service roads, board walks and other facilities
  • Formation of the landscape gardens
  • Sea view flagship Restaurant

Estimated construction time period: 28 months

Updated on July 2, 2026