Dredging

  • Inner and outer harbours will not be dredged but there will be dredging required to create the new navigational channel.
  • All material will be retained on site for the new beach and the extended boat storage area.
  • Only rocks will need to be brought into the site. Estimated to be around five months of traffic movement to bring in the rocks.
  • Will use silt barriers to contain dredged material.